Last month, we concluded the cultivation and development of Phase 2. This consisted of several dozen acres of Mango UHD and Melia Dubia (15x15 ft). During Phase 2, we also decided to proceed with inter-cropping of fodder crops. The large acreage required another sub-surface tank (SST) for irrigation.
Last year, we constructed our first tank. In case you missed reading that posting, you can find it here . This time around, we decided to use random rubble instead of bricks. The former has a significant cost advantage over bricks.
The new tank is 22 ft x 22 ft x 10 ft which translates into approx capacity of 1.35 lakh litres.
Steel reinforcement grid 8"x8" being laid to contain the hydrostatic pressure from the bottom of the tank
Construction of the side walls with random rubble.
Walls erected up to the ground level..
Tank ready, drip system installed!
Initial testing of tank at half capacity.
Last time around, inner and outer sides were plastered which led to budget overruns. This time, we did not plaster the walls, instead suffered from several leaks due to gaps and partially due to poor workmanship. Subsequently, we ended up plastering the exterior sides which seems to contain the leaks.
Due to different material and design, we were able to save considerably even though cost of cement and labor has increased in the last one year. We hope to be able to service the entire plantation between our two SST tanks including future Phase 3 needs.
Last year, we constructed our first tank. In case you missed reading that posting, you can find it here . This time around, we decided to use random rubble instead of bricks. The former has a significant cost advantage over bricks.
The new tank is 22 ft x 22 ft x 10 ft which translates into approx capacity of 1.35 lakh litres.
Steel reinforcement grid 8"x8" being laid to contain the hydrostatic pressure from the bottom of the tank
Construction of the side walls with random rubble.
Walls erected up to the ground level..
Tank ready, drip system installed!
Initial testing of tank at half capacity.
Last time around, inner and outer sides were plastered which led to budget overruns. This time, we did not plaster the walls, instead suffered from several leaks due to gaps and partially due to poor workmanship. Subsequently, we ended up plastering the exterior sides which seems to contain the leaks.
Due to different material and design, we were able to save considerably even though cost of cement and labor has increased in the last one year. We hope to be able to service the entire plantation between our two SST tanks including future Phase 3 needs.